House Extension 23/10/17—21/02/18

Start slideshow
23 Oct 17 - Day 1 The contractors have just arrived. The conservatory is still standing.
23 Oct 17 - End of Day 1 - the conservatory and the dwarf wall has been demolished and removed.
23 Oct 17 - End of Day 1 - The top layer of the crazy paving has been broken up and removed.
23 Oct 17 - End of Day 1 - The party wall has been demolished and removed.
24 Oct 17 - End of Day 2 - The conservatory floor has started to be broken up.
24 Oct 17 - End of Day 2 - and the area around the manhole is being prepared for its relocation into the driveway.
24 Oct 17 - End of Day 2 - A six foot hole has been excavated in the middle of the lawn to create a soak away.
25 Oct 17 - End of Day 3 - part of the footings have been excavated. These are approximately 1.5m deep.
25 Oct 17 - End of Day 3 - the sewer can be seen running through the footings.
25 Oct 17 - End of Day 3 - the Eucalyptus tree at the bottom of the garden has been cut down. This was necessary due to the amount of water it draws from the…